About This Project
Project Details
- Model Full EPC Lump Sum
- Schedule August 2020 – January 2022 (In service 2023)
Engineering, Procurement and Construction of a NPS 36 natural gas pipeline and associated facilities in Blueberry Rivers First Nation Territory and under British Columbia Oil & Gas Commission.
Project Scope Includes:
- 36 km of 36” Pipe
- 1.5 km of 16” pipe
- Horizontal Directional Drill Bores
- 1 x 36” (743m)
- 1 x 16” (530m)
- Horizontal Bores
- 12 x 36” (718m)
- 4 x 16” (329m)
- DLC Blending Facility
- Gas custody transfer metering facilities x 2 (Ovintiv & North River)
- Delivery facility