About This Project

Project Details

  • Model Full EPC Lump Sum
  • Schedule August 2020 – January 2022 (In service 2023)

Engineering, Procurement and Construction of a NPS 36 natural gas pipeline and associated facilities in Blueberry Rivers First Nation Territory and under British Columbia Oil & Gas Commission.

Project Scope Includes: 

  • 36 km of 36” Pipe
  • 1.5 km of 16” pipe
  • Horizontal Directional Drill Bores 
    • 1 x 36” (743m)
    • 1 x 16” (530m)
  • Horizontal Bores
    • 12 x 36” (718m)
    • 4 x 16” (329m)
  • DLC Blending Facility
  • Gas custody transfer metering facilities x 2 (Ovintiv & North River)
  • Delivery facility

Back to All Projects

Watch Video

Ready to get Started?

Contact us today and see why EPiC Solutions is the right choice to get your next project to the finish line.